How long does deemed conveyance take?

The new 120-day limit under the October 2026 GR, the time limits for stamp duty and registration, and what usually slows an application down.

Once the new online system is in force, the Competent Authority is to decide a deemed conveyance application within 120 days (four months), down from 180 days, under the GR of 23 October 2026. Stamp duty adjudication, registration and mutation follow, so the whole process from filing to the property card takes longer than the decision alone. These are the time limits the government has laid down; in practice, they often run much longer. The full process is in our deemed conveyance guide.

At a glance

  • Decision by the Competent Authority: 120 days under the 2026 GR, once the online system is live (180 days earlier)
  • Stamp duty adjudication: within 30 days of a complete application, where adjudication is needed
  • Registration: the Sub-Registrar is to register the deed within one day
  • Mutation: the society then applies to enter its name on the property card or 7/12

When can a society start?

Where the flat purchase agreements fix no period, the promoter must convey within four months of the registration of the society. Once that period has passed without a conveyance, the society may apply. There is no outer time limit: the Bombay High Court has held that MOFA obligations give rise to a continuing cause of action, so a society can apply many years later.

How long does the Competent Authority take to decide?

The GR of 23 October 2026 sets a time limit of 120 days, down from 180, and cuts the approval stages from four desks to two: office scrutiny, then the Competent Authority’s hearing and reasoned order. The new time limit applies once the online system on the Aaple Sarkar portal is ready; the GR does not fix a date.

What happens after the order, and how long does it take?

  1. Stamp duty. Where the deed records that no FSI is balance and every flat agreement was duly stamped, the society can register directly at ₹100 per flat. Otherwise the Collector of Stamps adjudicates the duty, within 30 days of a complete application.
  2. Registration. Many registration offices work with fewer officers than they need, and some are run by officers holding additional charge. Officers may be cautious about deeds they see less often, such as deemed conveyance deeds, and may decline to register when an Index II or another document is missing. The Sub-Registrar also issues notice to the developer as the law provides, and the hearing on that notice takes further time.
  3. Mutation. The society applies to the City Survey Officer or Talathi to enter its name on the property card or 7/12. The procedure is complete only then. In practice this step can take time of its own (see below).

How long does it take in practice?

The time limits above are what the government has laid down. In practice, they vary considerably, and a society should plan for delays at each stage.

  • Officers’ other responsibilities. Co-operation Department officers also carry other government duties, which take priority when the State needs them. In 2026, with drought declared in many talukas, department staff were deployed on drought work. From July to part of September 2026, the District Deputy Registrar for Pune City was also handling the electoral roll revision (SIR), the farm loan waiver and other assignments, so hearings and the signing of conveyance and transfer deeds in pending matters moved more slowly. This is a normal part of how government offices work, and it is worth allowing for.
  • Registration. Many registration offices are short of officers, and some are run by officers holding additional charge. Such officers sometimes refuse to register documents they are unfamiliar with, or refuse when an Index II or another document is missing. The Sub-Registrar also issues notice to the developer as the law provides, and the hearing on that notice takes further time.
  • Mutation. The Talathi sometimes issues a further notice before mutation, even though the State Government’s GR says no such notice is to be issued in deemed conveyance cases. The matter may then go for hearing before the Circle Officer, the Sub-Divisional Officer and beyond.
  • Changes by the developer. Some developers amend the plan midway, even without the flat owners’ consent, which extends the proceedings.
  • The unexpected. Any of these, or something else, can add time that no one could plan for.

What slows an application down?

  • Objections from the promoter, landowners or other societies in the layout
  • Landowners who have died or cannot be traced, whose heirs must be found and served
  • Missing documents that have to be obtained as certified copies
  • Disputes about how much land the society is entitled to, especially where several buildings or other structures share the plot

Questions about timing

How long does the Competent Authority have to decide a deemed conveyance application?

Under the GR of 23 October 2026, 120 days, down from 180 days, once the new online system on the Aaple Sarkar portal is in force.

Is there a deadline for a society to apply for deemed conveyance?

No. MOFA obligations give rise to a continuing cause of action, so a society can apply even many years after the promoter’s duty to convey arose.

How soon is the deed registered after the order?

Under the 2018 GR the Sub-Registrar is to register the deed within one day. Stamp duty adjudication, where needed, is to be decided within 30 days of a complete application.

Why does deemed conveyance take longer than the government’s timeline?

The time limits are what the government has laid down, but in practice officers also carry other government duties, registration offices work with fewer officers than they need, Sub-Registrars and Talathis may issue further notices and hold hearings, and developers sometimes amend the plan midway.